Thank you IJC. So very interesting to learn of the particular skills and knowledge required by all those involved including the wharf foreman.
As an aside - a large amount of the Station's switch/control gear is still preserved under security on the station. Switch House West (which borders the £1 million glass house apartments) is now structurally complete with fitting out just started. Work continues on Turbine Hall West, Boiler House, Pump House, Turbine Hal East and Switch House East.
Phase 3 will see the whole PS enclosed by glass house £1 million plus apartments. The smells from Cringle Street waste transfer station come free of charge.
Thanks again IJC.
BW
00